Bunker and Bag Storage Cost Comparison
John Roach, F&L Farm Business Consulting,
LLC
INTRODUCTION
Which method of horizontal forage storage is the most economical? The question has been addressed many times. This is my attempt using real life numbers to answer the question. As with any economic analysis, the results are dependent upon the assumptions used. It is impossible to develop a set of assumptions that will fit every producers situation. Therefore, as you review this analysis please keep in mind that you will have to adjust the end result based upon the practices used by your business.
As the numbers reveal, this is an important decision that every dairy business must address. It would be irresponsible of any manager to come to a meeting and make a decision based upon an analysis that was done on an example production unit. You must go through this type of an analysis for your business to get the correct answer for your situation. Use this analysis only for the purpose of insuring that you have addressed all of the variables when making your own calculations.
METHODS OF STORAGE
Method 1 Bunker Silo
ุ Bunker silo with (2) 35 foot haylage and (1) 80 foot corn silage bays
ุ Four-12 foot high poured-in-place walls
ุ Walls 160 feet in length
ุ Both ends open with 50 foot concrete aprons on each end
ุ Concrete floor
ุ Silage piled 4 feet over walls at the highest point
ุ Thirty feet of the apron on both ends used to pile feed
ุ Forage stored on 30 feet of both aprons, forage 6:1 ramp to 16 feet high.
ุ Storage and handling loss 20%
ุ Covered with plastic and truck tire sidewalls 1 tire/yd2
Method 2 Silo Bags
ุ Bag size 12 x 250 with 230 of usable storage length
ุ Bags stored on a 275pad (250asphalt for bag 25of gravel apron)
ุ Asphalt pad constructed with 2 - 2 layers of asphalt
ุ Gravel base compacted 8 of 3 breaker rock and 4 of พ gravel.
ุ Each bag will use 15 of pad width
ุ Storage and handling loss 5%
COMMON ASSUMPTIONS
Cattle
ุ 400 milking, 365 days/year
Diet
ุ 51 pounds of dry matter intake/cow/day
ุ 50% of the dry matter intake is from forage (25.5 pounds/cow/day)
ุ Forage is 50/50 corn silage, haylage
Feed Out Method
ุ Must be able to feed fully fermented forage 365 days/year
Labor
ุ Time to remove forage from storage is equal in both methods
ุ Labor to install tires and plastic charged at $12.00 per hour
ุ Feeding technician labor charged at $15.00 per hour
Equipment Repair
ุ Cost to maintain loading equipment is considered equal
BUNKER CAPITAL COSTS
150 x 160 with 4 walls and 50 apron on both ends
ุ Walls 640 with 7 footings @ $100/ft $ 64,000
ุ Concrete floor 24,000 ft2 @ $1.50/ft $ 36,000
ุ Concrete apron 15,000 ft2 @ $1.50/ft $ 22,500
ุ Excavating
- Strip 8 topsoil 968 yd3 @ $2.00/yd3 $1,935
- Site prep other 2,000 yd3 @ $2.25/yd3 $4,500
- Finish grading $ 800
- 4 พ" gravel @ $9.00/yd3 in place $4,230
- 10% contingency on excavating $1,147 $ 12,612
ุ
Tires 3,800 @ $1.5 each delivered $ 5,700
Total $140,812
ุ 20 year useful life based upon ft2
- Corn silage 53% of total $3,732
- Haylage 47% of total $3,309 $ 7,041
ุ Industrial Loader 8 year useful life @ $50,000 85% time
- Corn silage 50% of total $2,656
- Haylage 50% of total $2,656 $ 5,313
BAG CAPITAL COSTS
Pad 180 x 275 with a 25 gravel apron
ุ Asphalt 180 x 250 (2) 2 layers 45,000 ft2 @ $0.72/ ft2 $32,400
ุ Excavating
- Strip 8 topsoil 1,322yd3 @ $2.00/yd3 $ 2,457
- Site prep other 2,540 yd3 @ $2.25/yd3 $ 5,715
- Finish grading $ 1,016
- 8 of 3 1,228 yd3 @ $9.00/yd3 in place $11,055
- 4 of พ 623 yd3 @ $9.00/yd3 in place $ 5,610
- 10% contingency on excavating $ 2,822 $28,675
Total $61,075
ุ 20 year useful life
- Corn silage 50% of total $1,527
- Haylage 50% of total $1,527 $3,054
ุ Skidsteer 3 year useful life @ $22,000 25% time
- Corn silage 50% of total $1,833
- Haylage 50% of total $1,833 $3,666
BUNKER ANNUAL COSTS
Corn Silage Filling 1,127 tons DM harvested
ุ Packing time 45 hours @ $60/hr $2,700
ุ Finish packing 3 hours @ $60/hr $ 180
ุ Plastic 5 rolls 60 x 100 @ $248 ea. $1,240
ุ Labor tires/plastic on .75 minute/tire 2,000 tires @ $12/hr $ 300
ุ Labor tires off .94 minute/tire 2,000 tires @ $15/hr $ 470
ุ
Labor to remove spoiled feed .25 hrs/day @
$15/hr $1,369
Total $6,259
ุ Cost of 1 harvested acre of corn silage $ 276
Haylage filling 1,110 tons DM harvested
ุ Packing time 60 hours @ $60/hr $3,600
ุ Finish packing 6 hours @ $60/hr $ 360
ุ Plastic 2 roll 60 x 100 @ $248 ea. $ 496
ุ Plastic 2 roll 60 x 150 @ $371ea $ 742
ุ Labor tires/plastic on .75 minute/tire 1800 tires $12/hr $ 270
ุ Labor tires off .94 minute/tire 1,800 tires $15/hr $ 423
ุ
Labor to remove spoiled feed .5 hrs/day @
$15/hr $2,738
Total $8,629
ุ Cost of 1 harvested acre of haylage $ 234
BAG ANNUAL COSTS
Corn Silage filling 980 tons DM harvested, 163 ton DM stored in each
bag
ุ Bagging 6 bags @ $2,550/bag $15,300
ุ
Labor plastic off 1 hour/bag @ $15/hr $ 90
Total $15,420
Haylage filling 980 tons DM harvested, 163 ton DM stored in each bag
ุ Bagging 6 bags @ $2,550/bag $15,300
ุ
Labor plastic off 1 hour/bag @ $15/hr $ 90
Total $15,420
OTHER CONSIDERATIONS
There are other issues that need to be identified and discussed as we look at the issue of bunker or bags. In the case of an expanding dairy, owner equity is often a limiting factor in making the decision of bunker or bag. If equity allows only the construction of the milking center and cattle housing, bags may be the only option for expanded feed storage.
While cow numbers are increasing in an expanding dairy, the number of cow may not be sufficient to support the forage removal rate required by a bunker sized for steady state. Bunkers are more suited to a larger size dairy mainly due to forage removal rates.
There is a learning curve associated with managing a bunker. In an expansion, the manager is already juggling several other learning curves and may elect not to add one more. While learning to manage a bunker, forage quality often suffers in the first few years due to inadequate packing or poor covering among other factors. Providing high quality forage is key to profitability in any dairy. It is absolutely critical in an expanding dairy. Therefore, the decision to invest in a bunker system may be delayed until the newly expanded dairy has overcome its initial growing pains. Bags may be a good fit during this interim period.
SUMMARY CONSIDERATION
As the analysis shows, minimizing storage losses is the key. Given the assumptions used in this analysis, it appears that at a 20% storage loss rate for bunkers, storing corn silage in a bag or a bunker is a breakeven. With haylage stored in a bunker at a 20% storage loss bagging appears to have the edge.
Both bunkers and bagging are proven, effective methods of storing forage. Each has a known set of management points that need to be addressed if quality forage is to be provided to the end user, the cow. Each method has costs that are associated with the system. Each manager has to evaluate the management and cost issues and use the method that fits with their business.
F&L would like
to thank the following businesses for information used in completing this
analysis:
O&S
Harvesting,
KSI, Inc.,
Murphy Concrete
and Construction Company,
Schaumann's
Structure, Inc.,
|
Forage Storage Costs |
||||
|
|
|
|
|
|
|
|
Haylage |
Corn Silage |
||
|
|
Bag |
Bunker |
Bag |
Bunker |
|
Tons
Stored (dry matter) |
980 |
1,110 |
980 |
1,127 |
|
Annual
Costs |
|
|
|
|
|
Bunkers |
|
|
|
|
|
Packing |
|
3,960 |
|
2,880 |
|
Plastic |
|
1,238 |
|
1,240 |
|
Labor
tires/plastic on |
|
270 |
|
300 |
|
Labor
tires/plastic off |
|
423 |
|
470 |
|
Labor
remove spoil feed |
|
2,738 |
|
1,369 |
|
|
|
|
|
|
|
Bags |
|
|
|
|
|
Bag |
15,330 |
|
15,330 |
|
|
Labor
plastic off bags |
90 |
|
90 |
|
|
Total
cost |
$
15,420 |
$
8,629 |
$
15,420 |
$
6,259 |
|
Annual
cost/ton |
$
15.73 |
$
7.77 |
$
15.73 |
$
5.55 |
|
|
|
|
|
|
|
|
|
|
|
|
|
Capital
Costs 20yr |
|
|
|
|
|
Bunkers |
|
|
|
|
|
Bunker
walls |
|
1,504 |
|
1,696 |
|
Flat work
floors |
|
846 |
|
954 |
|
Flat work
aprons |
|
529 |
|
596 |
|
Excavation |
|
296 |
|
334 |
|
Tires |
|
135 |
|
150 |
|
Loader |
|
2,656 |
|
2,656 |
|
|
|
|
|
|
|
Bags |
|
|
|
|
|
Asphalt |
810 |
|
810 |
|
|
Excavation |
717 |
|
717 |
|
|
Skidsteer |
1,833 |
|
1,833 |
|
|
Total
cost |
$
3,360 |
$ 5,966 |
$
3,360 |
$
6,386 |
|
Capital
Cost/Ton |
$
3.43 |
$
6.09 |
$
3.43 |
$
6.52 |
|
Total
All Costs |
18,780 |
14,595 |
18,780 |
12,645 |
|
Total
Cost / ton |
$
19.16 |
$
13.15 |
$
19.16 |
$
11.22 |
|
|
|
|
|
|
|
Cost of
21 A Corn silage |
|
|
|
5,791 |
|
Cost of
29 A Haylage |
|
6,775 |
|
|
|
Total
All Costs |
|
21,370 |
- |
18,436 |
|
Total
Cost / ton |
|
$
19.25 |
|
$ 16.36 |