5/9/08
Project timeline:
Phase I - Discovery (November 2007 - April 2008)
- Stakeholder interviews and survey
- Staff survey
- External audience survey
- Analyze server stats and search logs
- Review “Contact Us” inquiries
Phase II - Planning and Kickoff (May 2008)
- Develop project plan and form project team
Phase III - Information Design (April -July 2008)
- Content audit
- Create sitemap of current top-level site
- Develop an intuitive information architecture
- Create wireframes
- Usability testing
- Develop an A to Z database of Extension sites
- Research current site search function and look for ways to improve
Phase IV - Visual Design (Fall 2008)
- Visual brainstorming and color selection
- Design prototypes
- Selection of final design
Phase V - Build & Integrate
- Code templates
- Test for accessibility compliance
- Migrate content to new templates
- Test, test, test
Phase VI - Launch (tentative, January 2009)